Dane Sabo NUCE 2122 - Summer 2025

Instructions:

Pick a metropolitan area in the US and identify the responsible electric utility. For that utility, summarize the following based on internet information:

  1. Number, type, MWE rating and age of power plants producing electricity for that utility
  2. Published strategy for new power plants to be added and plans for specific plants to be shutdown
  3. % of gas fired plants compared to coal, nuclear, and resource energy*

Send the completed summary to chris67ta@gmail.com

Submission

For my selection of a metropolitan area, I chose the Portland Oregon MSA.

There are two major electric utilities in Portland: Portland General Electric serves most of Portland west of the Wilamette River, while Pacific Power and Portland General Electric share the eastern side of the metro area.

Portland General Electric (PGE) will be the focus of this assignment, as they are the main supplier in Portland.

PGE has the following facility breakdown:

Active Facilities

Plant Name Plant Type Generation Capacity % of Cap Commissioned
Beaver Gen. Plnt. Comb. Cycle Nat. Gas 511 MWe 12.9% 1976
Port Westward High Eff. Gas Pwr. Plnt. Nat. Gas 607 MWe 15.3% 2007
Carty Gen. Plnt. Comb. Cycle Nat. Gas 436 MWe 11.0% 2016
Coyote Springs Gen. Plnt. Comb. Cycle Nat. Gas 257 MWe 6.5% 2003
Colstrip Pwr. Plnt. 3&4 Coal 296 MWe 7.5% 1984
Faraday Hydro 46 MWe 1.2% 1907
North Fork Hydro 58 MWe 1.5% 1958
Oak Grove Hydro 43 MWe 1.1% 1956
River Mill Hydro 25 MWe 0.6% 1911
T.W. Sullivan Hydro 18 MWe 0.5% 1889
Pelton Dam Hydro 57 MWe 1.4% 1958
Round Butte Dam Hydro 187 MWe 4.7% 1964
Biglow Canyon Wind 450 MWe (max) 11.4% 2005
Tucannon River Wind 267 MWe (max) 6.7% 2012
Marion County Waste-to-Energy 13 MWe 0.3% 1987
Clearwater Wind 311 MWe (max) 7.8% 2024
Wheatridge (Wind) Wind 300 MWe (max) 7.6% 2020
Wheatridge (Solar) Solar 50 MWe (max) 1.3% 2022
Wheatridge (Battery) Battery 30 MWe (max) 0.8% 2022

Percent Natural Gas: 45.7%
Percent Coal: 7.5%
Percent Hydro: 11.0%
Percent Wind: 33.5%
Percent Other: 2.3%

Decomissioned Facilities

Plant Name Plant Type Generation Capacity Decomissioned
Boardman Gen. Plnt. Coal 601 MWe 2020
Bull Run Hydro 22 MWe 2007
Trojan Nuclear Plnt. Nuclear 1130 MWe 1992

Plans for Future Plants

PGE's biggest plans for the future include the exit of investment from the Colstrip coal power plant, 3200 MW of Requests for Proposals for renewable sources and storages, and at least 500 MW of rooftop solar installations.

PGE, at the current moment, is looking to