\section{State of the Art and Limits of Current Practice} This research creates tractably safe autonomous reactor control systems. Understanding what we automate requires understanding how nuclear reactors operate today. This section examines reactor operators and their operating procedures, investigates the limitations of human-based operation, and reviews current formal methods approaches to reactor control systems. \subsection{Current Reactor Procedures and Operation} Nuclear plant procedures form a hierarchy: normal operating procedures govern routine operations, abnormal operating procedures handle off-normal conditions, Emergency Operating Procedures (EOPs) manage design-basis accidents, Severe Accident Management Guidelines (SAMGs) address beyond-design-basis events, and Extensive Damage Mitigation Guidelines (EDMGs) cover catastrophic damage scenarios. These procedures must comply with 10 CFR 50.34(b)(6)(ii); NUREG-0899 provides development guidance~\cite{NUREG-0899, 10CFR50.34}. Expert judgment and simulator validation—not formal verification—drive their development. Technical evaluation, simulator validation testing, and biennial review under 10 CFR 55.59~\cite{10CFR55.59} rigorously assess procedures. This rigor, however, cannot provide formal verification of key safety properties. No mathematical proof exists that procedures cover all possible plant states, that required actions complete within available timeframes, or that transitions between procedure sets maintain safety invariants. \textbf{LIMITATION:} \textit{Procedures lack formal verification of correctness and completeness.} Current procedure development relies on expert judgment and simulator validation. No mathematical proof exists that procedures cover all possible plant states, that required actions can be completed within available timeframes, or that transitions between procedure sets maintain safety invariants. Paper-based procedures cannot ensure correct application. Even computer-based procedure systems lack the formal guarantees automated reasoning could provide. Nuclear plants operate with multiple control modes: automatic control, where the reactor control system maintains target parameters through continuous reactivity adjustment; manual control, where operators directly manipulate the reactor; and various intermediate modes. In typical pressurized water reactor operation, the reactor control system automatically maintains a floating average temperature and compensates for power demand changes through reactivity feedback loops alone. Safety systems, by contrast, operate with implemented automation. Reactor Protection Systems trip automatically on safety signals with millisecond response times, and engineered safety features actuate automatically on accident signals without operator action required. The division between automated and human-controlled functions reveals hybrid control's fundamental challenge. Highly automated systems handle reactor protection---automatic trips on safety parameters, emergency core cooling actuation, containment isolation, and basic process control~\cite{WRPS.Description, gentillon_westinghouse_1999}. Human operators, however, retain control of strategic decision-making: power level changes, startup/shutdown sequences, mode transitions, and procedure implementation. \subsection{Human Factors in Nuclear Accidents} The previous subsection established that procedures lack formal verification despite rigorous development. Nuclear plants currently operate through written procedures executed by human operators. This human-centered approach defines current practice. We now examine why this reliance poses fundamental limitations. Current-generation nuclear power plants employ over 3,600 active NRC-licensed reactor operators in the United States~\cite{operator_statistics}. These operators divide into Reactor Operators (ROs), who manipulate reactor controls, and Senior Reactor Operators (SROs), who direct plant operations and serve as shift supervisors~\cite{10CFR55}. Staffing typically requires at least two ROs and one SRO for current-generation units~\cite{10CFR50.54}. Becoming a reactor operator requires several years of training. Human error persistently contributes to nuclear safety incidents despite decades of improvements in training and procedures. This persistence provides compelling motivation for formal automated control with mathematical safety guarantees. Operators hold legal authority under 10 CFR Part 55 to make critical decisions, including departing from normal regulations during emergencies. The Three Mile Island (TMI) accident demonstrated how personnel error, design deficiencies, and component failures combined to cause partial meltdown. Operators misread confusing and contradictory indications, then shut off the emergency water system~\cite{Kemeny1979}. The President's Commission on TMI identified a fundamental ambiguity: placing responsibility for safe power plant operations on the licensee without formal verification that operators can fulfill this responsibility does not guarantee safety. This tension between operational flexibility and safety assurance remains unresolved: the person responsible for reactor safety is often the root cause of failures. Multiple independent analyses converge on a striking statistic: 70--80\% of nuclear power plant events are attributed to human error, versus approximately 20\% to equipment failures~\cite{WNA2020}. More significantly, the root cause of all severe accidents at nuclear power plants---Three Mile Island, Chernobyl, and Fukushima Daiichi---has been identified as poor safety management and safety culture: primarily human factors~\cite{hogberg_root_2013}. A detailed analysis of 190 events at Chinese nuclear power plants from 2007--2020~\cite{zhang_analysis_2025} found that 53\% of events involved active errors, while 92\% were associated with latent errors---organizational and systemic weaknesses that create conditions for failure. \textbf{LIMITATION:} \textit{Human factors impose fundamental reliability limits that training alone cannot overcome.} Four decades of improvements have failed to eliminate human error. These limitations are fundamental to human-driven control, not remediable defects. \subsection{Formal Methods} Human factors impose fundamental reliability limits that training alone cannot overcome. Formal methods offer an alternative: mathematical guarantees of correctness that human-centered approaches cannot achieve. This subsection examines recent formal methods work in nuclear control and identifies their limitations for autonomous hybrid systems. \subsubsection{HARDENS} The High Assurance Rigorous Digital Engineering for Nuclear Safety (HARDENS) project represents the most advanced application of formal methods to nuclear reactor control systems to date~\cite{Kiniry2024}. HARDENS aimed to address a fundamental dilemma: existing U.S. nuclear control rooms rely on analog technologies from the 1950s--60s. This technology is obsolete compared to modern control systems and incurs significant risk and cost. The NRC contracted Galois, a formal methods firm, to demonstrate that Model-Based Systems Engineering and formal methods could design, verify, and implement a complex protection system meeting regulatory criteria at a fraction of typical cost. The project delivered a Reactor Trip System (RTS) implementation with full traceability from NRC Request for Proposals and IEEE standards through formal architecture specifications to verified software. HARDENS employed formal methods tools and techniques across the verification hierarchy. High-level specifications used Lando, SysMLv2, and FRET (NASA Formal Requirements Elicitation Tool) to capture stakeholder requirements, domain engineering, certification requirements, and safety requirements. Requirements were analyzed for consistency, completeness, and realizability using SAT and SMT solvers. Executable formal models used Cryptol to create a behavioral model of the entire RTS, including all subsystems, components, and limited digital twin models of sensors, actuators, and compute infrastructure. Automatic code synthesis generated verifiable C implementations and SystemVerilog hardware implementations directly from Cryptol models---eliminating the traditional gap between specification and implementation where errors commonly arise. Despite its accomplishments, HARDENS has a fundamental limitation directly relevant to hybrid control synthesis: the project addressed only discrete digital control logic without modeling or verifying continuous reactor dynamics. The Reactor Trip System specification and verification covered discrete state transitions (trip/no-trip decisions), digital sensor input processing through discrete logic, and discrete actuation outputs (reactor trip commands). The project did not address continuous dynamics of nuclear reactor physics. Real reactor safety depends on the interaction between continuous processes---temperature, pressure, neutron flux---evolving in response to discrete control decisions. HARDENS verified the discrete controller in isolation but not the closed-loop hybrid system behavior. \textbf{LIMITATION:} \textit{HARDENS addressed discrete control logic without continuous dynamics or hybrid system verification.} Verifying discrete control logic alone provides no guarantee that the closed-loop system exhibits desired continuous behavior such as stability, convergence to setpoints, or maintained safety margins. Beyond the technical limitation of omitting continuous dynamics, HARDENS also faced deployment maturity constraints. The project produced a demonstrator system at Technology Readiness Level 2--3 (analytical proof of concept with laboratory breadboard validation) rather than a deployment-ready system validated through extended operational testing. The NRC Final Report explicitly notes~\cite{Kiniry2024} that all material is considered in development, not a finalized product, and that ``The demonstration of its technical soundness was to be at a level consistent with satisfaction of the current regulatory criteria, although with no explicit demonstration of how regulatory requirements are met.'' The project did not include deployment in actual nuclear facilities, testing with real reactor systems under operational conditions, side-by-side validation with operational analog RTS systems, systematic failure mode testing (radiation effects, electromagnetic interference, temperature extremes), NRC licensing review, or human factors validation with licensed operators in realistic control room scenarios. \textbf{LIMITATION:} \textit{HARDENS achieved TRL 2--3 without experimental validation.} While formal verification provides mathematical correctness guarantees for the implemented discrete logic, the gap between formal verification and actual system deployment involves myriad practical considerations: integration with legacy systems, long-term reliability under harsh environments, human-system interaction in realistic operational contexts, and regulatory acceptance of formal methods as primary assurance evidence. \subsubsection{Sequent Calculus and Differential Dynamic Logic} HARDENS verified discrete control logic but omitted continuous dynamics—a fundamental limitation for hybrid systems. Other researchers pursued a complementary approach: extending temporal logics to handle hybrid systems directly. This work produced differential dynamic logic (dL). dL introduces two additional operators into temporal logic: the box operator and the diamond operator. The box operator \([\alpha]\phi\) states that for some region \(\phi\), the hybrid system \(\alpha\) always remains within that region. In this way, it is a safety ivariant being enforced for the system. The second operator, the diamond operator \(<\alpha>\phi\) says that for the region \(\phi\), there is at least one trajectory of \(\alpha\) that enters that region. This is a declaration of a liveness property. %source: https://symbolaris.com/logic/dL.html While dL allows for the specification of these liveness and safety properties, actually proving them for a given hybrid system is difficult. Automated proof assistants such as KeYmaera X exist to help develop proofs of systems using dL, but fail for reasonably complex hybrid systems. State space explosion and non-terminating solutions prevent creating system proofs using dL. %Source: that one satellite tracking paper that has the problem with the %gyroscopes overloding and needing to dump speed all the time Approaches have been made to alleviate these issues for nuclear power contexts using contract and decomposition based methods, but are far from a complete methodology to design systems with. %source: Manyu's thesis. Instead, these approaches have been used on systems that have been designed a priori, and require expert knowledge to create the system proofs. \textbf{LIMITATION:} \textit{Logic-based hybrid system verification has not scaled to system design.} While dL and related approaches can verify hybrid systems post-hoc, they require expert knowledge and have been applied only to systems designed a priori. State space explosion prevents their use in the design loop for complex systems like nuclear reactor startup procedures. \subsection{Summary: The Verification Gap} \textbf{State of the art:} Current practice reveals a fundamental gap. Human operators provide operational flexibility but introduce persistent reliability limitations—four decades of training improvements have failed to eliminate them. Formal methods provide correctness guarantees but have not scaled to complete hybrid control design. HARDENS verified discrete logic without continuous dynamics. Differential dynamic logic expresses hybrid properties but requires post-design expert analysis. No existing methodology synthesizes provably correct hybrid controllers from operational procedures with verification integrated into the design process. \textbf{The gap our work addresses:} This gap—between discrete-only formal methods and post-hoc hybrid verification—defines our challenge and motivates our approach. Closing it enables autonomous nuclear control with mathematical safety guarantees, directly addressing the economic constraints that threaten small modular reactor viability. The next section presents our methodology for bridging this gap through compositional hybrid verification.