\section{State of the Art and Limits of Current Practice}
|
|
|
|
The principal aim of this research is to create autonomous reactor control
|
|
systems that are tractably safe. But, to understand what exactly is being
|
|
automated, it is important to understand how nuclear reactors are operated
|
|
today. First, the reactor operator themselves is discussed. Then, operating
|
|
procedures that we aim to leverage later are examined. Next, limitations of
|
|
human-based operation are investigated, while finally we discuss current formal
|
|
methods based approaches to building reactor control systems.
|
|
|
|
\subsection{Current Reactor Procedures and Operation}
|
|
|
|
Current generation nuclear power plants employ 3,600+ active NRC-licensed
|
|
reactor operators in the United States. These operators are divided into Reactor
|
|
Operators (ROs) who manipulate reactor controls and Senior Reactor Operators
|
|
(SROs) who direct plant operations and serve as shift
|
|
supervisors~\cite{10CFR55}. Staffing typically requires 2+ ROs with at least one
|
|
SRO for current generation units. To become a reactor operator, an individual
|
|
might spend up to six years to pass required training~\cite{princeton}.
|
|
|
|
The role of human operators is paradoxically both critical and
|
|
problematic. Operators hold legal authority under 10 CFR Part 55 to make
|
|
critical decisions including departing from normal regulations during
|
|
emergencies. The Three Mile Island (TMI) accident demonstrated how
|
|
``combination of personnel error, design deficiencies, and component
|
|
failures'' led to partial meltdown when operators ``misread confusing
|
|
and contradictory readings and shut off the emergency water
|
|
system''~\cite{Kemeny1979}. The President's Commission on TMI identified
|
|
a fundamental ambiguity: placing ``responsibility and accountability for
|
|
safe power plant operations...on the licensee in all circumstances''
|
|
without formal verification that operators can fulfill this
|
|
responsibility under all conditions~\cite{Kemeny1979}. This tension
|
|
between operational flexibility and safety assurance remains unresolved
|
|
in current practice.
|
|
|
|
Nuclear plant procedures exist in a hierarchy: normal operating procedures for
|
|
routine operations, abnormal operating procedures for off-normal conditions,
|
|
Emergency Operating Procedures (EOPs) for design-basis accidents, Severe
|
|
Accident Management Guidelines (SAMGs) for beyond-design-basis events, and
|
|
Extensive Damage Mitigation Guidelines (EDMGs) for catastrophic damage
|
|
scenarios. These procedures must comply with 10 CFR 50.34(b)(6)(ii) and are
|
|
developed using guidance from NUREG-0899~\cite{NUREG-0899}, but their
|
|
development process relies fundamentally on expert judgment and simulator
|
|
validation rather than formal verification. Procedures undergo technical
|
|
evaluation, simulator validation testing, and biennial review as part of
|
|
operator requalification under 10 CFR 55.59~\cite{10CFR55}. Despite these
|
|
rigorous development processes, procedures fundamentally lack formal
|
|
verification of key safety properties. There is no mathematical proof that
|
|
procedures cover all possible plant states, that required actions can be
|
|
completed within available timeframes under all scenarios, or that transitions
|
|
between procedure sets maintain safety invariants.
|
|
|
|
\textbf{LIMITATION:} \textit{Procedures lack formal verification of correctness
|
|
and completeness.} Current procedure development relies on expert judgment and
|
|
simulator validation. No mathematical proof exists that procedures cover all
|
|
possible plant states, that required actions can be completed within available
|
|
timeframes, or that transitions between procedure sets maintain safety
|
|
invariants. Paper-based procedures cannot ensure correct application, and even
|
|
computer-based procedure systems lack the formal guarantees that automated
|
|
reasoning could provide.
|
|
|
|
Nuclear plants operate with multiple control modes: automatic control where the
|
|
reactor control system maintains target parameters through continuous rod
|
|
adjustment, manual control where operators directly manipulate control rods, and
|
|
various intermediate modes. In typical pressurized water reactor operation, the
|
|
reactor control system automatically maintains a floating average temperature,
|
|
compensating for changes in power demand with reactivity feedback loops alone.
|
|
Safety systems instead operate with implemented automation. Reactor
|
|
Protection Systems trip automatically on safety signals with millisecond
|
|
response times, and engineered safety features actuate automatically on accident
|
|
signals without operator action required.
|
|
|
|
The current division between automated and human-controlled functions
|
|
reveals the fundamental challenge of hybrid control. Highly
|
|
automated systems handle reactor protection like automatic trips on safety
|
|
parameters, emergency core cooling actuation, containment isolation,
|
|
and basic process control. Human operators, however, retain control of
|
|
strategic decision-making such as power level changes, startup/shutdown
|
|
sequences, mode transitions, and procedure implementation. %%%NEED MORE
|
|
|
|
\textbf{LIMITATION:} \textit{Current practice treats continuous plant
|
|
dynamics and discrete control logic separately.} No application of
|
|
hybrid control theory exists that could provide mathematical guarantees
|
|
across mode transitions, verify timing properties formally, or optimize
|
|
the automation-human interaction trade-off with provable safety bounds.
|
|
|
|
|
|
\subsection{Human Factors in Nuclear Accidents}
|
|
The persistent role of human error in nuclear safety incidents, despite
|
|
decades of improvements in training and procedures, provides perhaps the
|
|
most compelling motivation for formal automated control with
|
|
mathematical safety guarantees.
|
|
|
|
Multiple independent analyses converge on a striking statistic: 70--80\%
|
|
of all nuclear power plant events are attributed to human error versus
|
|
approximately 20\% to equipment failures~\cite{DOE-HDBK-1028-2009,WNA2020}. More
|
|
significantly, the International Atomic Energy Agency concluded that ``human
|
|
error was the root cause of all severe accidents at nuclear power plants''---a
|
|
categorical statement spanning Three Mile Island, Chernobyl, and Fukushima
|
|
Daiichi~\cite{IAEA-severe-accidents}. A detailed analysis of 190 events at
|
|
Chinese nuclear power plants from 2007--2020~\cite{Wang2025} found that 53\% of
|
|
events involved active errors while 92\% were associated with latent errors
|
|
(organizational and systemic weaknesses that create conditions for failure). The
|
|
persistence of this 70--80\% human error contribution despite four decades of
|
|
continuous improvements in operator training, control room design, procedures,
|
|
and human factors engineering. This suggests fundamental cognitive limitations
|
|
rather than remediable deficiencies.
|
|
|
|
The Three Mile Island Unit 2 accident on March 28, 1979 remains the definitive
|
|
case study in human factors failures in nuclear operations. The accident began
|
|
at 4:00 AM with a routine feedwater pump trip, escalating when a
|
|
pressure-operated relief valve (PORV) stuck open---draining reactor
|
|
coolant---but control room instrumentation showed only whether the valve had
|
|
been commanded to close, not whether it actually closed. When Emergency Core
|
|
Cooling System pumps automatically activated as designed, operators made the
|
|
fateful decision to shut them down based on their incorrect assessment of plant
|
|
conditions. The result was a massive loss of coolant accident and the core
|
|
quickly began to overheat. During the emergency, operators faced more than 100
|
|
simultaneous alarms, overwhelming their cognitive capacity~\cite{Kemeny1979}.
|
|
The core suffered partial meltdown with 44\% of the fuel melting before the
|
|
situation was stabilized. Quantitative risk analysis revealed the magnitude of
|
|
failure in existing safety assessment methods: the actual core damage
|
|
probability was approximately 5\% per year while Probabilistic Risk Assessment
|
|
had predicted 0.01\% per year---a 500-fold underestimation. This
|
|
dramatic failure demonstrated that human reliability could not be adequately
|
|
assessed through expert judgment and historical data alone.
|
|
|
|
\textbf{LIMITATION:} \textit{Human factors impose fundamental reliability
|
|
limits that cannot be overcome through training alone.} Response time
|
|
limitations constrain human effectiveness---reactor protection systems
|
|
must respond in milliseconds, 100--1000 times faster than human
|
|
operators. Cognitive biases systematically distort judgment:
|
|
confirmation bias, overconfidence, and anchoring bias are inherent
|
|
features of human cognition, not individual failings~\cite{Reason1990}.
|
|
The persistent 70--80\% human error contribution despite four decades of
|
|
improvements demonstrates that these limitations are fundamental
|
|
rather than remediable part of human-driven control.
|
|
|
|
\subsection{HARDENS and Formal Methods}
|
|
|
|
The High Assurance Rigorous Digital Engineering for Nuclear Safety (HARDENS)
|
|
project represents the most advanced application of formal methods to nuclear
|
|
reactor control systems to date. HARDENS aimed to address the nuclear industry's
|
|
fundamental dilemma: existing U.S. nuclear control rooms rely on analog
|
|
technologies from the 1950s--60s. This technology is woefully out of date
|
|
compared to modern control technoligies, and incurs significant risk and cost to
|
|
plant operation. The NRC contracted Galois to demonstrate that Model-Based
|
|
Systems Engineering and formal methods could design, verify, and implement a
|
|
complex protection system meeting regulatory criteria at a fraction of typical
|
|
cost. The project delivered a Reactor Trip System (RTS) implementation with full
|
|
traceability from NRC Request for Proposals and IEEE standards through
|
|
formal architecture specifications to formally verified binaries and
|
|
hardware running on FPGA demonstrator boards.
|
|
|
|
HARDENS employed an array of formal methods tools and techniques across the
|
|
verification hierarchy. High-level specifications used Lando, SysMLv2, and FRET
|
|
(NASA JPL's Formal Requirements Elicitation Tool) to capture stakeholder
|
|
requirements, domain engineering, certification requirements, and safety
|
|
requirements. Requirements were formally analyzed for consistency, completeness,
|
|
and realizability using SAT and SMT solvers. Executable formal models employed
|
|
Cryptol to create an executable behavioral model of the entire RTS including all
|
|
subsystems, components, and limited digital twin models of sensors, actuators,
|
|
and compute infrastructure. Automatic code synthesis generated formally
|
|
verifiable C implementations and System Verilog hardware implementations
|
|
directly from Cryptol models---eliminating the traditional gap between
|
|
specification and implementation where errors commonly arise.
|
|
|
|
Despite its accomplishments, HARDENS has a fundamental limitation directly
|
|
relevant to hybrid control synthesis: the project addressed only discrete
|
|
digital control logic without modeling or verifying continuous reactor dynamics.
|
|
The Reactor Trip System specification and formal verification covered discrete
|
|
state transitions (trip/no-trip decisions), digital sensor input processing
|
|
through discrete logic, and discrete actuation outputs (reactor trip commands).
|
|
However, the project did not address continuous dynamics of nuclear reactor
|
|
physics. Real reactor safety depends on the interaction between continuous
|
|
processes (temperature, pressure, neutron flux evolving according to
|
|
differential equations) and discrete control decisions (trip/no-trip, valve
|
|
open/close, pump on/off). HARDENS verified the discrete controller in isolation
|
|
but not the closed-loop hybrid system behavior.
|
|
|
|
\textbf{LIMITATION:} \textit{HARDENS addressed discrete control logic without
|
|
continuous dynamics or hybrid system verification.} Verifying discrete control
|
|
logic alone provides no guarantee that the closed-loop system exhibits desired
|
|
continuous behavior such as stability, convergence to setpoints, or maintained
|
|
safety margins.
|
|
|
|
HARDENS produced a demonstrator system at Technology Readiness Level 2--3
|
|
(analytical proof of concept with laboratory breadboard validation) rather than
|
|
a deployment-ready system validated through extended operational testing. The
|
|
NRC Final Report explicitly notes~\cite{Kiniry2022}: ``All material is
|
|
considered in development and not a finalized product'' and ``The demonstration
|
|
of its technical soundness was to be at a level consistent with satisfaction of
|
|
the current regulatory criteria, although with no explicit demonstration of how
|
|
regulatory requirements are met.'' The project did not include deployment in
|
|
actual nuclear facilities, testing with real reactor systems under operational
|
|
conditions, side-by-side validation with operational analog RTS systems,
|
|
systematic failure mode testing (radiation effects, electromagnetic
|
|
interference, temperature extremes), actual NRC licensing review, or human
|
|
factors validation with licensed nuclear operators in realistic control room
|
|
scenarios.
|
|
|
|
\textbf{LIMITATION:} \textit{HARDENS achieved TRL 2--3 without experimental
|
|
validation.} While formal verification provides mathematical correctness
|
|
guarantees for the implemented discrete logic, the gap between formal
|
|
verification and actual system deployment involves myriad practical
|
|
considerations: integration with legacy systems, long-term reliability
|
|
under harsh environments, human-system interaction in realistic
|
|
operational contexts, and regulatory acceptance of formal methods as
|
|
primary assurance evidence.
|